A set of Town of Hempstead deadlines gets repeated across the web as though it governed remodeling permits. It comes from the zoning ordinance and applies to Town Board approvals. The rules that actually govern a kitchen or bathroom permit sit in Town Code Chapter 86, and they are shorter clocks and much smaller money. This page quotes both, keeps them apart, and says what the Town does not publish.
PERMITTED WORK IN THE TOWN OF HEMPSTEAD
Kitchens and bathrooms on Long Island — demolition, rough plumbing, tile and the finished room.
Kitchen — Quartz Waterfall Island
Kitchen In Progress
Shower Tile Going In
Finished Bath — Marble Top
A Town of Hempstead building permit for a remodel runs on Town Code Chapter 86. Section 86-13A requires work to commence within 90 days of issuance, and section 86-13C deems a project abandoned if it is not completed within one year. Section 86-13D caps the extension fee between $50 and $120. Fees are not published online; call (516) 538-8500.
Because New York State wrote it that way. 19 NYCRR 1203.3(a)(1) requires every authority having jurisdiction to require building permits for work that must conform to the Codes. It then lets localities exempt eight categories, two of which matter for a kitchen or a bathroom: “painting, wallpapering, tiling, carpeting, or other similar finish work,” and “repairs, provided that the work does not have an impact on fire and life safety.” The State mandates the permit for regulated work and merely permits the exemption for cosmetic work. Nassau County contains three towns, two cities and 64 incorporated villages, and each of those departments makes its own choice. That is why the answer genuinely varies, and why a rule you read about one town does not transfer to the next one.
The Town of Hempstead is also the hardest Nassau department to research. As of July 2026, hempsteadny.gov blocks automated access entirely. The department address and phone number on this page come from the Town's own form BD-11 rather than from its website: Department of Buildings, 1 Washington Street, Hempstead, NY 11550-4923, (516) 538-8500. Confirm both before you drive there. That inaccessibility is also why a good deal of secondhand Hempstead permit content is stale, and why one particular error has spread.
The correction. Building Zone Ordinance Art. XXVI § 260 opens with this sentence: “Any special exception, site plan approval or GSS District inclusion granted by the Town Board shall expire and be of no force and effect, unless…” Everything that follows — the four months to obtain the permit, the four months to begin work, the two years to a certificate of occupancy, and the $350 extension fee at § 260.1 — hangs off that opening clause. Those are zoning-approval deadlines attached to Town Board actions.
An interior kitchen or bathroom remodel does not go before the Town Board, and it is not governed by § 260. An ordinary remodel permit is governed by Town Code Chapter 86, which gives you 90 days to start rather than four months, one year to finish rather than two years, and an extension fee of $50 to $120 rather than $350. If you have budgeted or scheduled a Hempstead remodel around the longer numbers, you have roughly half the runway you think you have.
The two instruments are easy to conflate because they both belong to the Town of Hempstead and both talk about expiry. They are not the same document, they do not have the same subject, and only one of them reaches a homeowner replacing a bathroom. Here they are side by side.
| Clock | Building Zone Ordinance Art. XXVI § 260 — Town Board zoning approvals | Town Code Chapter 86 — building and plumbing permits |
| What the instrument governs | “Any special exception, site plan approval or GSS District inclusion granted by the Town Board” | Building and plumbing permits issued by the Department of Buildings |
| Reaches an interior kitchen or bathroom remodel? | No — an interior remodel is not a Town Board approval | Yes — this is the ordinary remodel permit |
| Time to obtain the permit | Four months from the Town Board's grant, or the approval expires | Not applicable; the permit itself starts the Chapter 86 clocks |
| Time to begin work | Four months from issuance | § 86-13A: “work shall commence within 90 days of the date of issuance” |
| Outside limit on the project | Two years to a certificate of occupancy | § 86-13C: not completed “within one year from the date of issuance… it shall be deemed abandoned” |
| Extension fee | § 260.1: $350 | § 86-13D: “25% of the total fees charged for the issuance of such permit, but shall not be less than $50 nor exceed $120” |
Read the right-hand column and nothing else if your project is an interior remodel. Ninety days is a real constraint on Long Island, because lining up a crew, a dumpster and a plumber in the same week takes time. The one-year clock catches custom work: a shower enclosure, a stone top or a cabinet order that slips twice can put a small bathroom past twelve months without anybody noticing the date.
The governing sentence is § 86-9A, which requires permits for construction, alterations and installations, “except that no permit shall be required for the performance of ordinary repairs which are not structural in nature.” That is the whole published test. Chapter 86 does not itemise cabinets, countertops, tile, flooring or paint, and it does not publish a scope-by-scope list of the kind some towns issue.
It is a reasonable reading that new cabinet doors, a countertop and a backsplash in an unchanged layout are ordinary repairs which are not structural in nature. It is a reading, not a quotation, and the Town has not said it. Contrast the Town of Islip, which publishes a dated permit-trigger sheet stating in its own words that no permit is required for finish work such as paint, wallpaper, tile, carpet and cabinets. Hempstead publishes no equivalent, so in Hempstead the determination belongs to the Department of Buildings and the only safe move on a borderline kitchen is a phone call to (516) 538-8500 before demolition, not after.
The permit side of a kitchen is less ambiguous. Moving a sink so the drain and vent have to be re-run, running gas to a range that never had it, adding circuits for a wall oven, and taking out the wall between the kitchen and the dining room are alterations and installations in the ordinary sense of § 86-9A. Each also brings in a licensed trade under Chapter 86 or Chapter 84.
The same section governs, and the same absence of an itemised list applies. What changes is the density of the work. A bathroom concentrates supply, waste and vent piping, a receptacle circuit, a light and a fan into forty or fifty square feet, so it reaches the permit side of § 86-9A faster than a kitchen of the same budget.
Two specific consequences are worth having in front of you. First, § 86-13C names plumbing permits explicitly alongside building permits, so a bathroom job commonly runs two permits on the same one-year abandonment clock. Second, the plumbing application is not yours to file. Under § 86-10D, applications for plumbing work “shall be made by licensed master plumbers on forms prescribed by the Commissioner of Buildings.” If you have not retained a plumber, you cannot start the filing, which makes plumber selection a scheduling milestone rather than a later decision.
Converting a tub to a curbless shower, moving a toilet even a short distance, or adding a second sink all mean new soil, waste or vent piping. Adding a bathroom rather than renovating one is a larger conversation about structure and drainage — we cover it on bathroom remodeling in Nassau County.
| Scope | How it reads against Town Code § 86-9A | What the Town publishes |
| Kitchen: cabinets, countertop, backsplash tile, flooring and paint in an unchanged layout | Turns on whether it is an ordinary repair which is not structural in nature | No itemised list. Chapter 86 does not name cabinets, countertops, tile, flooring or paint. |
| Kitchen: sink or dishwasher relocated, second sink added to an island | Reads as an alteration and installation — permit territory | § 86-9A covers construction, alterations and installations. |
| Kitchen: gas piping run to a range or cooktop | Reads as an installation — permit territory | § 86-9A. Gas piping is not within the ordinary-repair exception on any reading. |
| Kitchen or bath: wall removed to open the room | Structural — outside the ordinary-repair exception | The exception is limited to repairs “which are not structural in nature.” |
| Bathroom: shower retiled, floor retiled, walls painted, accessories changed | Turns on the same ordinary-repair test | No itemised list. Ask the Department of Buildings. |
| Bathroom: toilet or vanity relocated, tub converted to a curbless shower | New soil, waste or vent piping — plumbing permit territory | § 86-10D: the plumbing application is made by a licensed master plumber. |
| Bathroom: new receptacle circuit, fan or light wiring | Installation and wiring of electrical apparatus | Ch. 84 § 84-5A requires a Town of Hempstead master electrician licence for professional work. |
| Either room: new bathroom or kitchen created in previously unfinished space | Construction and alteration — permit territory | § 86-9A, and § 86-18B for the certificate at the end. |
Plumbing first. § 86-10D provides that “Applications for plumbing work… shall be made by licensed master plumbers on forms prescribed by the Commissioner of Buildings.” A Town of Hempstead master plumber licence exists, so the plumber on a Hempstead bathroom is not simply someone with a county registration. Retain him before the building application goes in; the plumbing filing is his to make.
Electrical is regulated separately and more aggressively. Chapter 84 covers master electricians, and § 84-5A provides that “no person shall engage in the installation and wiring of electrical apparatus in the Town of Hempstead in a professional capacity until such person shall apply for and obtain a master electrician's license.” The penalty at § 84-20 is unusual for Long Island: a violation is “punishable by a fine of not more than $1,000 or by imprisonment for not more than 30 days, or by both… Each day of continued violation shall constitute a separate additional offense.” Read the last clause carefully. The exposure is not a single $1,000 fine; it multiplies by the day the condition persists.
§ 84-19A authorises the Examining Board to certify and approve electrical inspection agencies. No roster is published and none could be retrieved as of July 2026, so we are not going to name one. Ask the Department of Buildings which agencies it accepts before your electrician orders an inspection.
Our own carpenters and project managers run your job start to finish. Electrical and plumbing are performed by licensed Nassau and Suffolk trade contractors we've worked with for years — we schedule them, we coordinate the inspections, and we're accountable for the result. Greene Group Construction holds Nassau County HIC #EF-65498 and Suffolk County HIC #HI-72958. We do not hold a Town of Hempstead trade licence, and under § 86-10D and § 84-5A those licences sit with the tradesmen who do the work.
We cannot tell you, and neither can anyone else honestly, because the Town of Hempstead fee schedule was not retrievable as of July 2026. The Town's website blocks automated access, so the schedule could not be read. We are not going to approximate it from a neighbouring town's or a village's figures. Nassau jurisdictions price by flat fee, by square foot, by thousand dollars of construction cost and by fixture, so a borrowed number is a wrong answer in a confident tone.
Two Hempstead figures are known, both from the Town's own documents. § 86-13D sets the permit extension fee at “25% of the total fees charged for the issuance of such permit, but shall not be less than $50 nor exceed $120.” Separately, form BD-11 prices a Building Department Record Search Sheet at $40 — the search you run when you are buying a house and want to know what was permitted in it. Form BD-11 also states that applications inactive for 90 days are abandoned and that fees are non-refundable and non-transferable, which is a real cost if a package stalls waiting on a document.
| Item | Status as of July 2026 | Source or next step |
| Permit trigger language | Published | Town Code § 86-9A |
| Itemised list of exempt cosmetic work | Not published | Chapter 86 gives only the ordinary-repair exception |
| Time to commence work | Published — 90 days | § 86-13A |
| Completion / abandonment period | Published — one year | § 86-13C |
| Permit extension fee | Published as a formula — 25%, $50 minimum, $120 maximum | § 86-13D |
| Building permit fee schedule | Not retrievable | Call (516) 538-8500 |
| Record search fee | Published — $40 | Form BD-11, Building Department Record Search Sheet |
| Application review time | No day count published | § 86-12A: approve or disapprove “within a reasonable time” |
| Permit turnaround time | Not published | True of every Long Island jurisdiction we examined |
| Approved electrical inspection agencies | No roster published | § 84-19A authorises certification; ask the department |
| Certificate of occupancy requirement | Published | § 86-18B, and § 86-19(1) for the certificate of completion |
| Online portal capabilities | Not verified | An OpenGov portal is linked from the Town's Online Permit Center |
With a certificate, and Chapter 86 provides for two. § 86-18B provides that no altered building may be occupied until a certificate of occupancy is issued. § 86-19(1) provides that work performed under a permit cannot be maintained beyond one year without a certificate of completion. Those two sections and the one-year abandonment rule at § 86-13C point the same direction: Hempstead expects a remodel to be finished, inspected and certified inside twelve months of issuance.
On timing, § 86-12A requires the inspector to “approve or disapprove the application within a reasonable time.” There is no published day count behind that phrase.
Only if you are in an unincorporated part of the Town. The Town of Hempstead's Department of Buildings permits the Town's unincorporated areas. Roughly 22 incorporated villages sit inside the Town's boundaries, and each of those villages runs its own building department with its own application, its own fee schedule and sometimes its own plumber and electrician licences. We are not publishing a named list of them. The enumerated village lists we could reach do not reconcile with each other and several villages straddle town lines, and a list that is wrong in one entry is the list that sends a homeowner to the wrong counter.
Here is how to settle it in five minutes instead. Your property tax bill is the definitive practical test. Villages levy their own taxes, so if a village tax appears as its own line on your bill, you are in that village and you file with that village. If there is no village line, you are in an unincorporated area and the Town is your department. Second, the Nassau County Land Records Viewer at lrv.nassaucountyny.gov is searchable by address and carries assessment roll, district and tax map information; district information is where the answer lives. Third, call the Town at (516) 538-8500 — if the answer is “not us,” they will generally tell you which village it is.
One warning applies across Nassau: a mailing address is not a jurisdiction. ZIP codes and post office names were drawn for mail delivery, and in this county a single familiar place name can cover several separate incorporated villages plus unincorporated town area.
An improvement can raise an assessment, and New York's Home Improvement Exemption under RPTL § 421-f is designed to phase that in: 100% of the increase is exempt in year one, declining 12.5 percentage points a year across years two through eight. The improvement must exceed $3,000, the greater portion of the building by square footage must be at least five years old, ordinary maintenance does not qualify, and adoption is opt-in by locality. The Town of Hempstead has adopted it, by Local Law 93-62.
We are not publishing a dollar figure for Hempstead. The statutory landscape moved on January 1, 2026, when the special-assessing-unit provision was repealed, and published local pages have not all caught up. Confirm the current exemption amount, eligibility and filing window with Nassau County Assessment at (516) 571-1500 before you count on it. This is general information, not tax, legal or code advice.
Permit fees are a small line inside a much larger number. Our published planning ranges run from about $12,000 for a surface bathroom refresh to $250,000 and above for high-end custom kitchen work; the detail sits in our Long Island kitchen remodel cost guide and our bathroom remodel cost guide. For the full service picture start at kitchen remodeling or bathroom remodeling, and for how Hempstead's rules sit beside North Hempstead's and Oyster Bay's see kitchen remodeling in Nassau County.
Permit questions get urgent when a kitchen or bathroom is being rebuilt after a failed supply line or a leaking shower pan. The damage rarely stops at the finishes, and the subfloor, joists and the ceiling below need assessing before anyone talks about tile. Greene Group Construction runs water damage restoration and insurance claims support as real service lines, so documentation, mitigation, permitting and the finished rebuild sit under one contract instead of three. Structural work runs through our general contracting division, and the debris leaves with our own junk removal and cleanout crews.
Do I need a permit to remodel a kitchen in the Town of Hempstead?
Town Code section 86-9A requires a permit for construction, alterations and installations, except that no permit shall be required for the performance of ordinary repairs which are not structural in nature. Chapter 86 does not itemise cabinets, countertops, tile, flooring or paint, so the Town publishes no list telling you which kitchen finishes fall inside that exception. Anything that moves plumbing, adds gas piping, alters wiring or takes out a wall is an alteration. Call the Department of Buildings at (516) 538-8500 with your scope before you assume either answer.
Do I need a permit to remodel a bathroom in the Town of Hempstead?
The same section governs, and a bathroom concentrates more plumbing and electrical work into less floor area than any other room, so most bathroom projects reach the permit side quickly. Section 86-10D provides that applications for plumbing work shall be made by licensed master plumbers on forms prescribed by the Commissioner of Buildings, which means the plumbing filing is not the homeowner's to make. The Town publishes no itemised list of exempt bathroom finishes. Confirm your scope with the Department of Buildings at (516) 538-8500.
How long is a Hempstead building permit good for?
Chapter 86 sets two clocks. Section 86-13A provides that work shall commence within 90 days of the date of issuance. Section 86-13C provides that if any project for which a building or plumbing permit has been issued has not been completed within one year from the date of issuance, it shall be deemed abandoned. The extension fee is set by section 86-13D at 25% of the total fees charged for the issuance of such permit, but shall not be less than $50 nor exceed $120.
Do the four-month and two-year Town of Hempstead deadlines apply to a kitchen or bathroom remodel?
No. Those deadlines come from Building Zone Ordinance Article XXVI section 260, which opens by providing that any special exception, site plan approval or GSS District inclusion granted by the Town Board shall expire and be of no force and effect unless its conditions are met. They are zoning-approval deadlines for Town Board actions, and section 260.1 sets a $350 extension fee for them. An interior kitchen or bathroom remodel does not go before the Town Board. Chapter 86 governs the ordinary remodel permit: 90 days to start work, one year before the project is deemed abandoned.
Who can file a Hempstead plumbing permit?
A licensed master plumber. Town Code section 86-10D provides that applications for plumbing work shall be made by licensed master plumbers on forms prescribed by the Commissioner of Buildings. A Town of Hempstead master plumber licence exists, so line the plumber up before you file rather than after. Greene Group Construction holds Nassau County HIC #EF-65498 and Suffolk County HIC #HI-72958 and does not hold a Town of Hempstead trade licence; under section 86-10D the Town-licensed master plumber makes the plumbing filing.
Does the Town of Hempstead require a licensed electrician for a kitchen or bathroom?
Chapter 84 governs master electricians. Section 84-5A provides that no person shall engage in the installation and wiring of electrical apparatus in the Town of Hempstead in a professional capacity until such person shall apply for and obtain a master electrician's license. Section 84-20 makes a violation punishable by a fine of not more than $1,000 or by imprisonment for not more than 30 days, or by both, and provides that each day of continued violation shall constitute a separate additional offense. Section 84-19A authorises the Examining Board to certify electrical inspection agencies; no roster of approved agencies is published, so ask the department which agencies it accepts.
What does a Town of Hempstead building permit cost?
The Town of Hempstead fee schedule was not retrievable as of July 2026, because hempsteadny.gov blocks automated access. Two figures are known from the Town's own documents. Section 86-13D sets a permit extension fee of 25% of the total fees charged for the issuance of such permit, not less than $50 and not more than $120. Form BD-11 prices a Building Department Record Search Sheet at $40. Call the Department of Buildings at (516) 538-8500 for the current schedule rather than budgeting from a neighbouring town's figures.
Does the Town of Hempstead issue my permit, or does a village?
The Town's Department of Buildings permits the unincorporated areas of the Town of Hempstead. Roughly 22 incorporated villages sit inside the Town's boundaries, and a village runs its own building department with its own application, its own fees and sometimes its own trade licences. The definitive practical test is your property tax bill: villages levy their own taxes, so a village tax billed as a separate line means you file with that village. You can also check district information in the Nassau County Land Records Viewer, or call the Town at (516) 538-8500 and ask.
Planning a kitchen or bathroom in the Town of Hempstead? Call (631) 532-7346 and we will walk your scope against Chapter 86 rather than against a deadline someone copied out of the zoning ordinance. For the other Long Island building departments, start at our Long Island remodeling permits hub. For the projects themselves, see kitchen remodeling and bathroom remodeling, or go county-wide with kitchen remodeling in Nassau County and bathroom remodeling in Nassau County. You can also request a free estimate.
RELATED SERVICES
NASSAU COMMUNITIES WE SERVE
One company for demolition, debris hauling, structural work and the finished kitchen or bathroom — filed and inspected under the Chapter 86 rules that actually apply to your project.